Release End Week

Project
Release
Group By
Horizontal Group by

Type / Activity Planned Actual Delay By(Weeks) Moved By Reason
Begin Release W25 W25 0 - -
End Release W35 W40 5 - -
Moved Log 4 Times
1 W35 W36 1 Randy Change of Direction
2 W36 W37 2 Doughlas Estimation Wrong
3 W37 W39 4 Randy Unplanned Work
4 W39 W40 5 Randy Dependancy